# 002004388104
Unscheduled inspection
Start date: 2020-03-06, end date: 2020-03-26, duration: —
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the execution of previously issued regulations dated 06/12/2019 43092019481
# 002004278740
Unscheduled inspection
Start date: 2020-01-23, end date: —, duration: —
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001904046817
Unscheduled inspection
Start date: 2019-10-22, end date: 2019-11-19, duration: —
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance with the regulations of the Volga Administration of Rostechnadzor dated 30092019 43092019370 of the appeal of Eurostyle LLC to the Volga Administration of Rostechnadzor notification of the elimination of violations bx 56479c dated 09102019 ex 698 dated 08102019
# 001903008395
Unscheduled inspection
Start date: 2019-07-01, end date: 2019-07-26, duration: —
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of a previously issued prescription
# 00170802980614
Unscheduled inspection
Start date: 2017-12-11, end date: 2017-12-15, duration: —
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the fulfillment by a legal entity of a previously issued instruction on the elimination of identified violations of the mandatory requirements specified in p19 of the regulation of 19062017 4321137136
# 00170802826248
Unscheduled inspection
Start date: 2017-10-31, end date: 2017-11-02, duration: —
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the fulfillment by a legal entity of a previously issued instruction on the elimination of identified violations of the mandatory requirements specified in paragraphs 118 of the regulation of 19062017 4321137136the tasks of this audit are to verify the elimination of violations specified in paragraphs 118 of the regulation of 19062017 4321137136the subject of this audit is the fulfillment of the instructions of the state control and supervision authorities
# 162101531067
Unscheduled inspection
Start date: 2021-12-09, end date: 2021-03-26, duration: 8
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 11/29/2021 case No. 13-11-2020/0052.The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.7. The subject of this review is (select the appropriate one): compliance with mandatory requirements and/or requirements established by municipal legal acts;
# 162101451132
Unscheduled inspection
Start date: 2021-12-09, end date: —, duration: 8
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 11/30/2021 case No. 13-11-2020/0051. The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.7. The subject of this review is (select the appropriate one): ☐ compliance with mandatory requirements and/or requirements established by municipal legal acts;☑ compliance of the information contained in the notification of the commencement of certain types of business activities with the mandatory requirements;
# 162101448858
Unscheduled inspection
Start date: 2021-12-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162101523142
Unscheduled inspection
Start date: 2021-12-29, end date: —, duration: 1
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 12/22/2021 case No. 13-11-2021/0061.The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.7. The subject of this review is (select the appropriate one): ☑ compliance with mandatory requirements and/or requirements established by municipal legal acts;
# 162101495153
Unscheduled inspection
Start date: 2021-12-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162101448867
Unscheduled inspection
Start date: 2021-12-15, end date: —, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 11/15/2021 case No. 13-11-2021/0003. The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements and/or requirements established by municipal legal acts.
# 162101456609
Unscheduled inspection
Start date: 2021-12-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162101357098
Unscheduled inspection
Start date: 2021-11-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162101328438
Unscheduled inspection
Start date: 2021-11-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162101346604
Unscheduled inspection
Start date: 2021-11-16, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 11/08/2021 case No. 13-11-2021/0027.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
The subject of this audit is (select the appropriate one):
compliance with mandatory requirements and (or) requirements established by municipal legal acts;
# 162101220905
Unscheduled inspection
Start date: 2021-10-14, end date: —, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 09/24/2021 case No. 13-11-2021/0041.The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.7. The subject of this audit is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts;
# 162101220041
Unscheduled inspection
Start date: 2021-10-14, end date: —, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 09/24/2021 case No. 13-11-2021/0040.The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.7. The subject of this audit is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts;
# 162101062730
Unscheduled inspection
Start date: 2021-10-01, end date: —, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 08/03/2021 case No. 13-11-2021/0003. The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements and/or requirements established by municipal legal acts.;
# 162100677020
Unscheduled inspection
Start date: 2021-09-13, end date: —, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipment of capital construction facilities with metering devices for energy resources used, availability of a construction permit, compliance with the requirements of Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; warning as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of design documentation; compliance with mandatory requirements and (or) requirements established by municipal legal acts.
# 162100699120
Unscheduled inspection
Start date: 2021-09-14, end date: —, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 08/03/2021 case No. 13-11-2021/0027.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
# 162100799424
Unscheduled inspection
Start date: 2021-09-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100803008
Unscheduled inspection
Start date: 2021-09-20, end date: —, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 08.10.2019 case No. 13-11-2019/0012.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
The subject of this audit is (to select the appropriate one):
☑ compliance with mandatory requirements and (or) requirements established by municipal legal acts;
# 162100471630
Unscheduled inspection
Start date: 2021-08-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100423614
Unscheduled inspection
Start date: 2021-08-09, end date: 2021-03-17, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/11/2021 case No. 13-11-2021/0004.
The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.7. The subject of this review is (select the appropriate one): ☑ compliance with mandatory requirements and/or requirements established by municipal legal acts;
# 162100282165
Unscheduled inspection
Start date: 2021-06-10, end date: —, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 06/08/2021 case No. 13-11-2020/0013.
The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
# 162100264687
Unscheduled inspection
Start date: 2021-06-07, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162100262564
Unscheduled inspection
Start date: 2021-06-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100255466
Unscheduled inspection
Start date: 2021-06-01, end date: —, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 11.11.2020 case No. 13-11-2020/0015.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
# 162100230924
Unscheduled inspection
Start date: 2021-05-21, end date: —, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, design documentation, and other regulations (norms and rules), as well as to draw up an act on the elimination of violations, based on the Inspection notification dated 05/19/2021 No. 4822 on the elimination of violations during construction, reconstruction of the capital construction facility, which was ordered to eliminate within the period established by the regulation dated 04/9/2021 No. 13-12/0114-01, until 05/31/2021.
# 162100155002
Unscheduled inspection
Start date: 2021-04-19, end date: 2021-04-21, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of execution of the order dated 12.02.2021 No. 13-12/0040-01, the deadline for which expired on 12.04.2021 and the preparation of an act based on the results of the inspection.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
The subject of this audit is: compliance with the regulations of state control (supervision) bodies, municipal control bodies;
# 162100152823
Unscheduled inspection
Start date: 2021-04-15, end date: 2021-05-14, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: Pursuant to Order No. 73 dated 04/02/2021 on conducting unscheduled on-site inspections of the working safety conditions of foreign citizens involved in the implementation of major investment projects, Minutes of the operational meeting of the Security Council of the Russian Federation No. Pr-356, approved by the President of the Russian Federation V.V. Putin on February 23, 2021, Motivated presentation by the head of the Department I.A. Semenova16/3-870-21- PV dated 04/12/2021
# 162100193493
Unscheduled inspection
Start date: 2021-04-30, end date: —, duration: 1
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 09/17/2020 case No. 13-11-2020/0051.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.7. The subject of this review is (select the appropriate one): ☐ compliance with mandatory requirements and/or requirements established by municipal legal acts;☑ compliance of the information contained in the notification of the commencement of certain types of business activities with the mandatory requirements;
# 162100183696
Unscheduled inspection
Start date: 2021-04-27, end date: —, duration: 14
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Respublike Tatarstan (Tatarstan)
Purpose of inspection: supervision and control over the fulfillment of mandatory requirements of the legislation of the Russian Federation
# 162100116346
Unscheduled inspection
Start date: 2021-04-05, end date: 2021-04-09, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 Of the Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/17/2020 case No. 13-11-2020/0012, the objectives of this inspection are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, violations of compliance performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is: compliance with mandatory requirements and (or) requirements established by municipal legal acts
# 162100168686
Unscheduled inspection
Start date: 2021-04-26, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 02/05/2021 case No. 13-11-2021/0003. The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements and/or requirements established by municipal legal acts.
# 162100168597
Unscheduled inspection
Start date: 2021-04-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100036496
Unscheduled inspection
Start date: 2021-03-02, end date: 2021-03-02, duration: 1
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of compliance of the performed works, applied in the process of construction of a capital construction facility of building materials, the results of such works with the requirements of design documentation; prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction, on the basis of an agreement with the developer or the customer; compliance with mandatory requirements or requirements established by municipal legal acts.
# 162100093069
Unscheduled inspection
Start date: 2021-03-25, end date: 2021-03-26, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 02/04/2021 case No. 13-11-2020/0052.The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.7. The subject of this review is (select the appropriate one): ☑ compliance with mandatory requirements and/or requirements established by municipal legal acts;
# 162100140087
Unscheduled inspection
Start date: 2021-03-22, end date: 2021-03-31, duration: 8
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: It is carried out for the purpose of:
– checking the fulfillment of the instruction of the Volga Administration of Rostechnadzor No. 43-09-2020-358 dated 12/24/2020.
The objectives of this audit are to monitor the implementation of previously issued regulations.
The subject of this audit is:
the fulfillment of an instruction issued by the state construction supervision authority on the elimination of violations of mandatory requirements.
# 162105349574
Unscheduled inspection
Start date: 2021-02-09, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162105323616
Unscheduled inspection
Start date: 2021-01-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162105311856
Unscheduled inspection
Start date: 2021-01-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162005273162
Unscheduled inspection
Start date: 2020-12-14, end date: 2020-12-15, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 17092020 case 131120200051 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162005273244
Unscheduled inspection
Start date: 2020-12-17, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162005254504
Unscheduled inspection
Start date: 2020-12-02, end date: 2020-12-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 27112020 case 131120200071the objectives of this inspection are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162005291284
Unscheduled inspection
Start date: 2020-12-28, end date: 2020-12-28, duration: 1
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 24122020 case 131120200052 The objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer of the work performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162005256864
Unscheduled inspection
Start date: 2020-12-10, end date: 2020-12-10, duration: 1
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the fact of the execution of the order dated 24082020 1412020201, the deadline for which expired on 01/12020, and to draw up an act based on the results of the inspection.
# 162005235539
Unscheduled inspection
Start date: 2020-11-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162005186827
Unscheduled inspection
Start date: 2020-10-19, end date: 2020-10-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 300-42020 case 131120200013 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162005200575
Unscheduled inspection
Start date: 2020-10-26, end date: 2020-10-28, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 17092020 case 131120200051 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162005173702
Unscheduled inspection
Start date: 2020-10-08, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162005177384
Unscheduled inspection
Start date: 2020-10-12, end date: 2020-10-14, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 300-42020 case 131120200012 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162005176643
Unscheduled inspection
Start date: 2020-10-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162005177280
Unscheduled inspection
Start date: 2020-10-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004471964
Unscheduled inspection
Start date: 2020-08-04, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162004474579
Unscheduled inspection
Start date: 2020-08-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004470388
Unscheduled inspection
Start date: 2020-08-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004470596
Unscheduled inspection
Start date: 2020-08-03, end date: 2020-08-21, duration: 15
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 24072020 case 131120200016 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004457971
Unscheduled inspection
Start date: 2020-08-03, end date: 2020-08-12, duration: 8
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of fulfillment of the instruction from 11062020 1312017701, the deadline for which has expired 10072020, and to draw up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations and other regulations. regulatory legal acts and project documentation The subject of this audit is the fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 162004492195
Unscheduled inspection
Start date: 2020-08-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004483750
Unscheduled inspection
Start date: 2020-08-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004481124
Unscheduled inspection
Start date: 2020-08-12, end date: 2020-09-10, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 300-42020 case 131120200015 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004486200
Unscheduled inspection
Start date: 2020-08-14, end date: 2020-08-21, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules, as well as to draw up an act on the elimination of violations based on the Inspection notification dated 10082020 8347 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by the regulation from 10082020 1412018101 to 21082020 The objectives of this audit are to prevent as well as identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The subject of this audit is to comply with the instructions of state control bodies, supervision bodies, and municipal control bodies
# 162004478192
Unscheduled inspection
Start date: 2020-08-10, end date: 2020-08-11, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of fulfillment of the prescription from 15072020 1312023701, the deadline for which has expired 31072020, and to draw up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and suppress violations of compliance by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations performed during the construction of a capital construction facility. regulatory legal acts and project documentation The subject of this audit is the fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 162004466645
Unscheduled inspection
Start date: 2020-07-28, end date: 2020-07-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 300-42020 case 131120200014 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004466730
Unscheduled inspection
Start date: 2020-07-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004445312
Unscheduled inspection
Start date: 2020-07-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004451466
Unscheduled inspection
Start date: 2020-07-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004451453
Unscheduled inspection
Start date: 2020-07-13, end date: 2020-07-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 300-42020 case 131120200014 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004451449
Unscheduled inspection
Start date: 2020-07-13, end date: 2020-07-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 300-42020 case 131120200013 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004451438
Unscheduled inspection
Start date: 2020-07-13, end date: 2020-07-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 300-42020 case 131120200012 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004455502
Unscheduled inspection
Start date: 2020-07-15, end date: 2020-07-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 09072020 case 131120200036 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004426083
Unscheduled inspection
Start date: 2020-06-08, end date: 2020-06-10, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of fulfillment of the order dated 13052020 1312012801, the deadline for which expired on 29052020, and to draw up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations and other regulations. regulatory legal acts and project documentation The subject of this audit is the fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 162004440268
Unscheduled inspection
Start date: 2020-06-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004423599
Unscheduled inspection
Start date: 2020-06-04, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162004423434
Unscheduled inspection
Start date: 2020-06-04, end date: 2020-06-08, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 300-42020 case 131120200014 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004423432
Unscheduled inspection
Start date: 2020-06-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004425995
Unscheduled inspection
Start date: 2020-06-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004431625
Unscheduled inspection
Start date: 2020-06-17, end date: 2020-06-19, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 250-52020 case 140420190033 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004429389
Unscheduled inspection
Start date: 2020-06-15, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162004429380
Unscheduled inspection
Start date: 2020-06-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004406098
Unscheduled inspection
Start date: 2020-05-08, end date: 2020-05-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 300-42020 case 131120200013 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004409503
Unscheduled inspection
Start date: 2020-05-18, end date: 2020-05-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 300-42020 case 131120200012 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004409485
Unscheduled inspection
Start date: 2020-05-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004403221
Unscheduled inspection
Start date: 2020-04-30, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 002004388104
Unscheduled inspection
Start date: 2020-03-06, end date: 2020-03-26, duration: —
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the execution of previously issued regulations dated 06/12/2019 43092019481
# 162004360224
Unscheduled inspection
Start date: 2020-03-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004335851
Unscheduled inspection
Start date: 2020-03-12, end date: 2020-03-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 05/122019 case 140420190033 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004254749
Unscheduled inspection
Start date: 2020-02-07, end date: 2020-02-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 05/122019 case 140420190033 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004187771
Unscheduled inspection
Start date: 2020-01-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 002004278740
Unscheduled inspection
Start date: 2020-01-23, end date: 2020-01-29, duration: —
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The tasks of this audit are the state control over compliance with industrial safety requirements during the operation of hazardous production facilities and the assessment of actions and omissions performed by the organization to identify and suppress violations by a legal entity in the field of industrial energy security in order to take urgent measures to prevent the possibility of causing damage to industrial energy security in the field of industrial energy security in the field of industrial energy security in the field of industrial energy security in the field of industrial energy security in the field of industrial energy security in the field of industrial energy security in the field of industrial energy security in the field of industrial energy security in the field of industrial energy security in the field of industrial energy security in the field of industrial energy security in the field of industrial energy security in the field of industrial energy security in the field of harm to the life and health of citizens
# 162004250789
Unscheduled inspection
Start date: 2020-01-24, end date: 2020-01-28, duration: —
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Monitoring of the fulfillment by a legal entity of a previously issued instruction to eliminate an identified violation of the mandatory requirement specified in paragraph 1 of the instruction from 20082019 4321137211the tasks of this audit are to verify the elimination of violations specified in paragraph 1 of the instruction from 20082019 4321137211the purpose of this audit is to comply with the instructions of state control bodies supervision bodies of municipal control
# 161904061770
Unscheduled inspection
Start date: 2019-12-09, end date: 2019-12-11, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 08102019 case 131120190012the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation7 carried out by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation7the subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161904094680
Unscheduled inspection
Start date: 2019-12-12, end date: 2019-12-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied in the process of construction of the capital construction facility of building materials and the results of such works with the requirements of the design documentation prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, compliance with mandatory requirements or requirements established by municipal legal acts
# 161903984478
Unscheduled inspection
Start date: 2019-11-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903913733
Unscheduled inspection
Start date: 2019-11-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903961299
Unscheduled inspection
Start date: 2019-11-08, end date: 2019-12-05, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms Reasoned submission to the State Labor Inspectorate 16364919PV dated 08112019
# 161903919904
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-12-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 08102019 case 131120170065the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation7 carried out by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation7the subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161903852120
Unscheduled inspection
Start date: 2019-10-21, end date: —, duration: —
Authority: —
Purpose of inspection: