Found 15 inspections:

# 002004315670
Unscheduled inspection
Start date: 2020-02-25, end date: 2020-02-27, duration:
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to monitor the implementation of the order dated January 20, 2020 21G3320K101THE objectives of this audit are to monitor the measures taken by a legal entity to comply with the order and comply with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility, to take measures to eliminate violations of mandatory requirements if they are identified and to bring to justice those who have violated the requirements of Federal laws. The purpose of the audit is to comply with the instructions of the state control and supervision body.


# 002004235355
Unscheduled inspection
Start date: 2020-02-17, end date: —, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Moskovskoi oblasti
Purpose of inspection:


# 001902771220
Unscheduled inspection
Start date: 2019-05-30, end date: —, duration:
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 002004315617
Unscheduled inspection
Start date: 2020-02-25, end date: 2020-03-05, duration:
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to prevent violations of legislation on urban development activities, including project documentation. The objectives of this audit are to monitor the measures taken to comply with the mandatory requirements of legislation on urban development by a legal entity during the construction reconstruction of a capital construction facility, to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation and to take measures to eliminate violations of mandatory requirements in the event of their identification and prosecution of persons who have committed violations of the requirements of Federal laws and other regulatory legal acts, the subject of this audit is the compliance of the work performed and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation project documentation with taking into account the changes made to the design documentation in accordance with parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 of Article 52 The Urban Planning Code of the Russian Federation


# 002004315670
Unscheduled inspection
Start date: 2020-02-25, end date: 2020-02-27, duration:
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to monitor the implementation of the order dated January 20, 2020 21G3320K101THE objectives of this audit are to monitor the measures taken by a legal entity to comply with the order and comply with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility, to take measures to eliminate violations of mandatory requirements if they are identified and to bring to justice those who have violated the requirements of Federal laws. The purpose of the audit is to comply with the instructions of the state control and supervision body.


# 002004235355
Unscheduled inspection
Start date: 2020-02-17, end date: 2020-03-17, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Moskovskoi oblasti
Purpose of inspection: This inspection is carried out in order to monitor the implementation of the order 117154 of December 13, 2017, previously issued by the state fire supervision authority.


# 002004192222
Unscheduled inspection
Start date: 2020-01-15, end date: 2020-01-20, duration:
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to monitor the implementation of the order dated January 21, 2019 31G3320K101THE objectives of this audit are to monitor the measures taken by a legal entity to comply with the order and comply with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility, to take measures to eliminate violations of mandatory requirements if they are identified and to bring to justice those who have violated the requirements of Federal laws. The purpose of the audit is to comply with the instructions of the state control and supervision body.


# 001904030773
Unscheduled inspection
Start date: 2019-11-29, end date: 2019-12-12, duration:
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used for construction, compliance with the requirements established by parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 001902771220
Unscheduled inspection
Start date: 2019-05-30, end date: 2019-06-25, duration:
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 001902620028
Unscheduled inspection
Start date: 2019-03-14, end date: 2019-03-27, duration:
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts. The purpose of this check is to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used the availability of a construction permit requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 001902435417
Unscheduled inspection
Start date: 2019-01-17, end date: 2019-01-21, duration:
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to monitor the implementation of the regulation dated September 17, 2018 700G3320K101. The objectives of this audit are to monitor the measures taken by the legal entity to comply with the regulation and comply with the mandatory requirements of legislation on urban development during the construction and reconstruction of a capital construction facility, to take measures to eliminate violations of mandatory requirements if they are identified and to bring to justice those who violations of the requirements of Federal laws and other regulatory legal acts 7 The subject of verification is the fulfillment of the instructions of the state control and supervision body


# 001800614029
Unscheduled inspection
Start date: 2018-09-04, end date: 2018-09-17, duration:
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: To review the documents of a legal entity related to the performance of work, including individual works, building structures, sections of engineering and technical support networks, as well as the use of building materials and products


# 001800560708
Unscheduled inspection
Start date: 2018-08-07, end date: 2018-08-13, duration:
Authority: Upravlenie gosudarstvennogo aviacionnogo nadzora i nadzora za obespecheniem transportnoi bezopasnosti po Centralnomu federalnomu okrugu
Purpose of inspection: Monitoring of compliance with the instructions of the UGAN NOTB of the Central Federal District of Rostransnadzor dated 26.012018 VM4177414011


# 501802025147
Unscheduled inspection
Start date: 2018-06-26, end date: 2018-07-23, duration:
Authority: Gosudarstvennaya inspekciya truda v Moskovskoi oblasti
Purpose of inspection: Protection of the rights and interests of employees and employers in accordance with the consideration of the appeal of Kuznetsov OV 7730718OB dated 31052018, the objectives of this audit are supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms. The subject of this audit is to note the necessary compliance with mandatory requirements and or requirements established by municipal legal acts


# 50170802877522
Unscheduled inspection
Start date: 2017-11-21, end date: —, duration:
Authority:
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.