# 772100243334
Unscheduled inspection
Start date: 2021-05-27, end date: 2021-06-18, duration: 16
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit:
to carry out control measures in connection with the verification of the fulfillment of the instruction, based on the expiration of the deadline for the execution by a legal entity of the instruction issued by Mosgosstroynadzor on the elimination of identified violations of mandatory requirements dated 11/17/2020 No. 36/20P.
Tasks:
prevention, detection and suppression of violations by legal entities engaged in activities in the field of industrial safety, their managers and other officials, their authorized representatives of the requirements established by Federal Law No. 116-FZ of July 21, 1997 "On Industrial Safety of Hazardous Production Facilities", other federal laws and other laws adopted in accordance with them regulatory legal acts of the Russian Federation in the field of industrial safety.
Subject:
verification of the elimination of violations specified in the regulation dated 11/17/2020 No. 36/20P (with a deadline of 05/18/2021) issued by Mosgosstroynadzor, based on the expiration of the deadline for the execution of the issued order by a legal entity.
# 772005204335
Unscheduled inspection
Start date: 2020-10-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004427608
Unscheduled inspection
Start date: 2020-06-09, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772004296723
Unscheduled inspection
Start date: 2020-02-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004232105
Unscheduled inspection
Start date: 2020-01-24, end date: 2020-01-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor
# 771903893735
Unscheduled inspection
Start date: 2019-10-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 771903872623
Unscheduled inspection
Start date: 2019-10-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 771903870829
Unscheduled inspection
Start date: 2019-10-21, end date: 2019-10-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: carrying out control measures in connection with the implementation of the inspection program on the basis of the approved inspection program dated 09.012018 The objectives of this audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development activities committed by the audited person
# 771903895563
Unscheduled inspection
Start date: 2019-10-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803211904
Unscheduled inspection
Start date: 2018-08-23, end date: 2018-08-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803154351
Unscheduled inspection
Start date: 2018-06-13, end date: 2018-06-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803125533
Unscheduled inspection
Start date: 2018-04-17, end date: 2018-04-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803078088
Unscheduled inspection
Start date: 2018-02-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802732950
Unscheduled inspection
Start date: 2017-10-17, end date: 2017-10-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802506754
Unscheduled inspection
Start date: 2017-09-19, end date: —, duration: —
Authority: —
Purpose of inspection: