# 422100062374
Unscheduled inspection
Start date: 2021-03-18, end date: 2021-03-24, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose: compliance of the work performed and the construction materials used, as well as the results of such work, with the requirements of project documentation; task: compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban development; subject: compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban development.
# 422105299294
Unscheduled inspection
Start date: 2021-01-12, end date: 2021-01-22, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose: compliance of the completed works and applied building materials, as well as the results of such work with the requirements of design documentation; tasks: determining the compliance of the constructed object with the requirements of design documentation and the requirements of the legislation of the Russian Federation in the field of urban development; subject: compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban development.
# 422004417524
Unscheduled inspection
Start date: 2020-05-25, end date: 2020-05-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: compliance of the work performed and the construction materials used as well as the results of such work with the requirements of the project documentation task compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban development subject compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban development
# 422004393322
Unscheduled inspection
Start date: 2020-04-09, end date: 2020-04-09, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: verification of the execution of the order of 24012020 03012001 the task of eliminating violations committed during the construction of a capital construction facility the subject of the execution of the order of 24012020 03012001
# 422004209284
Unscheduled inspection
Start date: 2020-01-21, end date: 2020-01-24, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the project documentation tasks compliance with the requirements of the legislation of the Russian Federation on urban development activities during the construction of the capital construction facility subject compliance with the requirements of the legislation of the Russian Federation on urban development activities