# 472004995168
Unscheduled inspection
Start date: 2020-09-30, end date: 2020-10-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the inspection program The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used parts 2 3 and 31 of Article 52 of the Urban Development Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation
# 782101316756
Unscheduled inspection
Start date: 2021-10-28, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: b) proverki rabot, ukazannyh v izveschenii lica, osuschestvlyayuschego stroitelstvo, o srokah zaversheniya rabot, kotorye podlezhat proverke
izveschenie o srokah ot 07.09.2021 № 03-5589/2020-10, so srokom zaversheniya etapa 30.09.2021.;
a) soblyudenie obyazatelnyh trebovanii, v tom chisle:
sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov;
# 782100476006
Unscheduled inspection
Start date: 2021-08-16, end date: —, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Cel: proverka rabot, ukazannyh v izveschenii lica, osuschestvlyayuschego stroitelstvo, o srokah zaversheniya rabot, kotorye podlezhat proverke
izveschenie o srokah zaversheniya rabot, kotorye podlezhat proverke ot 30.07.2021 № 03-2746/2020-8; proverka zaversheniya rabot, predusmotrennyh programmoi provedeniya proverok ot 08.06.2021 goda po delu № ZH 04-21(20), etap rabot – montazh konstrukcii nadzemnoi chasti, srok po programme 05.07.2021.
Predmet:soblyudenie obyazatelnyh trebovanii, v tom chisle: sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov; vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii.
# 782100329025
Unscheduled inspection
Start date: 2021-06-28, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:
# 782100109754
Unscheduled inspection
Start date: 2021-03-31, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: proverki zaversheniya rabot, predusmotrennyh programmoi provedeniya proverok ot «21» oktyabrya 2020 goda po delu № ZH 04-28(20) etap rabot - montazh fundamentov, srok po programme 30.01.2021;
soblyudenie obyazatelnyh trebovanii, v tom chisle:
sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov;
nalichie razresheniya na stroitelstvo;
vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii;
vypolnenie predpisanii komiteta gosudarstvennogo stroitelnogo nadzora i
gosudarstvennoi ekspertizy Leningradskoi oblasti;
v) provedenie meropriyatii:
po predotvrascheniyu prichineniya vreda zhizni, zdorovyu grazhdan, vreda zhivotnym, rasteniyam, okruzhayuschei srede;
po preduprezhdeniyu vozniknoveniya chrezvychainyh situacii prirodnogo i tehnogennogo haraktera;
po likvidacii posledstvii prichineniya takogo vreda.
# 782100104404
Unscheduled inspection
Start date: 2021-03-10, end date: —, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: b) proverki rabot, ukazannyh v izveschenii lica, osuschestvlyayuschego stroitelstvo, o srokah zaversheniya rabot, kotorye podlezhat proverke
izveschenie o srokah zaversheniya rabot po podgotovke zemelnogo uchastka i zaversheniyu zemlyanyh rabot vh. № 03-12161/2020-1 ot 09.02.2021;
zh) proverki zaversheniya rabot, predusmotrennyh programmoi provedeniya proverok ot 07.12.2021 po delu № ZH 04-31(20) (zavershenie rabot po podgotovke zemelnogo uchastka i zemlyanye raboty - 28.02.2021);
a) soblyudenie obyazatelnyh trebovanii, v tom chisle:
sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov;
nalichie razresheniya na stroitelstvo;
vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii;
b) vypolnenie predpisanii komiteta gosudarstvennogo stroitelnogo nadzora i
gosudarstvennoi ekspertizy Leningradskoi oblasti;
v) provedenie meropriyatii:
po predotvrascheniyu prichineniya vreda zhizni, zdorovyu grazhdan, vreda zhivotnym, rasteniyam, okruzhayuschei srede;
po preduprezhdeniyu vozniknoveniya chrezvychainyh situacii prirodnogo i tehnogennogo haraktera;
po likvidacii posledstvii prichineniya takogo vreda.
# 782100060022
Unscheduled inspection
Start date: 2021-02-04, end date: 2021-03-04, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Cel: proverki zaversheniya rabot, predusmotrennyh programmoi provedeniya proverok. Predmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii, v tom chisle: sootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov, proektnoi dokumentacii, v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii.
# 472005317447
Unscheduled inspection
Start date: 2020-12-21, end date: 2021-01-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of the completion of the work provided for in the inspection program The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 782005237277
Unscheduled inspection
Start date: 2020-11-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 472005190483
Unscheduled inspection
Start date: 2020-10-19, end date: 2020-11-16, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the completion of the work provided for in the inspection program The subject of this check is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources. requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 472004449095
Unscheduled inspection
Start date: 2020-07-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 472004458334
Unscheduled inspection
Start date: 2020-07-16, end date: 2020-08-12, duration: 4
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the inspection program The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used parts 2 3 and 31 of Article 52 of the Urban Development Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation
# 782004473457
Unscheduled inspection
Start date: 2020-07-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 472004437417
Unscheduled inspection
Start date: 2020-06-25, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:
# 472004409181
Unscheduled inspection
Start date: 2020-05-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 472004382918
Unscheduled inspection
Start date: 2020-03-25, end date: 2020-04-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 472004382916
Unscheduled inspection
Start date: 2020-03-25, end date: 2020-04-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 471903894292
Unscheduled inspection
Start date: 2019-10-23, end date: 2019-11-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 471903901388
Unscheduled inspection
Start date: 2019-10-30, end date: 2019-11-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 471903901348
Unscheduled inspection
Start date: 2019-10-30, end date: 2019-11-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction