Found 37 inspections:

# 002005155082
Unscheduled inspection
Start date: 2020-10-01, end date: 2020-10-07, duration: 5
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to control the execution of LLC LukBelOil of the previously issued order on the elimination of identified violations from 19042019 0790904191241 on the basis of the request of LLC LukBelOil to conduct an inspection from 14092020 ex 1711 and a notice on the elimination of violations of bn from 04092020 during the construction of the reconstruction of the capital construction facility Case 2386 "Arrangement of the Western part of the Guryanovskoye field of the Saratov region The first stage" located at Saratov region, Rivne district, Tarlykovsky municipality, former lands of SEC Tarlykovsky, the objectives of this audit are to verify the elimination by a legal entity of the violations identified in the regulation on the elimination of violations of 19042019 0790904191241 The subject of this audit is the fulfillment by the audited person of the regulation on the elimination of violations of 19042019 0790904191241 on the basis of a petition from LukBelOil LLC to conduct an audit from 14092020 ex 1711 and notices on the elimination of violations of bn from 04092020


# 002004236866
Unscheduled inspection
Start date: 2020-01-24, end date: 2020-01-31, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is carried out in order to monitor the implementation of paragraphs 117 of the previously issued order dated October 21, 2019 138821019074 PL The purpose of this audit is to carry out measures to control the supervision of the elimination of LLC LukBelOil TIN 6454044627 of identified violations of mandatory requirements reflected in the previously issued order dated October 21, 2019 138821019074 PL the deadline for which expired on October 21, 2020 The subject of this audit is the fulfillment by the audited persons paragraphs 117 of the previously issued regulation dated October 21, 2019 138821019074 PL


# 001902683212
Unscheduled inspection
Start date: 2019-04-23, end date: 2019-05-27, duration:
Authority: Gosudarstvennaya inspekciya truda v Saratovskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing norms of labor law consideration of a written request from a citizen


# 001902448596
Unscheduled inspection
Start date: 2019-01-24, end date: 2019-02-06, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to control the compliance of the completed works with the mandatory requirements of the design documentation requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility based on the inspection program Case 6404450917 C "Development of the Western part of the Guryanovskoye field of the Saratov region First stage" located at the address of the Russian Federation Saratov region Rivne district Tarlykovsky municipality former lands of the SEC "Tarlykovsky" the objectives of this audit are to prevent, identify and suppress violations of the legislation on urban development, including project documentation, committed by the developer, the customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, the subject of this audit is the compliance of the work and materials used in the construction of the specified capital construction facility, as well as the results of such work with the requirements of project documentation in accordance with the including the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources in accordance with the program for conducting checks on the availability of a construction permit compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 001800009490
Unscheduled inspection
Start date: 2018-01-19, end date: 2018-02-01, duration:
Authority: NizhneVolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this check is carried out in order to control the elimination of identified violations of the mandatory requirements specified in the Regulation dated 301/12017 476028 upon expiration of the deadline for execution, the deadline expired on 09.012018


# 00170802901067
Unscheduled inspection
Start date: 2017-11-22, end date: 2017-12-05, duration:
Authority: NizhneVolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: compliance with the mandatory requirements of the previously issued legal regulation 408828 on the elimination of violations during the construction of a capital construction facility dated October 20, 2017


# 00170701394458
Unscheduled inspection
Start date: 2017-02-16, end date: 2017-02-28, duration:
Authority: NizhneVolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the audit is carried out in order to verify the fulfillment of paragraphs 141 deadline for the elimination of violations 01022017 of the previously issued order dated 27102016 P4200 on the elimination of identified violations of mandatory requirements in connection with the expiration of their deadlines, the purpose of this audit is the implementation of measures to control the supervision of the elimination of LLC LukBelOil of identified violations of mandatory requirements reflected in the previously issued order dated 27102016 P4200, the deadline for which has expired 01022017 The objectives of this audit are to comply with the requirements of the state control and supervision bodies


# 00150600017759
Unscheduled inspection
Start date: 2015-07-01, end date: 2015-07-03, duration:
Authority: NizhneVolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the fulfillment of the points of violations specified in the previously issued prescription


# 002005230451
Unscheduled inspection
Start date: 2020-11-16, end date: 2020-12-11, duration: 20
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the real test is conducted to monitor compliance of the performed works with the mandatory requirements of the project documentation requirements on energy saving and improvement of energy efficiency in the reconstruction of the object of capital construction in accordance with the notice of completion of construction of the facility "construction of the Western part Granovskogo field Saratov region the First stage" located at Saratov oblast Rivne reionsation of this test is to verify compliance with the mandatory requirements of the legislation on town-planning including project documentation, developer technical customer and the person in charge of the construction on the basis of the contract with the developer or technical zakazchikami this review is of the compliance of contractors and construction materials used in the process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of the town planning code of the project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of the town planning code of the Russian Federation or information the model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources to the availability of building permits compliance with the requirements of parts 2 3 and 31 St 52 of the town planning code of the Russian Federation


# 002005155082
Unscheduled inspection
Start date: 2020-10-01, end date: 2020-10-07, duration: 5
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to control the execution of LLC LukBelOil of the previously issued order on the elimination of identified violations from 19042019 0790904191241 on the basis of the request of LLC LukBelOil to conduct an inspection from 14092020 ex 1711 and a notice on the elimination of violations of bn from 04092020 during the construction of the reconstruction of the capital construction facility Case 2386 "Arrangement of the Western part of the Guryanovskoye field of the Saratov region The first stage" located at Saratov region, Rivne district, Tarlykovsky municipality, former lands of SEC Tarlykovsky, the objectives of this audit are to verify the elimination by a legal entity of the violations identified in the regulation on the elimination of violations of 19042019 0790904191241 The subject of this audit is the fulfillment by the audited person of the regulation on the elimination of violations of 19042019 0790904191241 on the basis of a petition from LukBelOil LLC to conduct an audit from 14092020 ex 1711 and notices on the elimination of violations of bn from 04092020


# 002004236866
Unscheduled inspection
Start date: 2020-01-24, end date: 2020-01-31, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is carried out in order to monitor the implementation of paragraphs 117 of the previously issued order dated October 21, 2019 138821019074 PL The purpose of this audit is to carry out measures to control the supervision of the elimination of LLC LukBelOil TIN 6454044627 of identified violations of mandatory requirements reflected in the previously issued order dated October 21, 2019 138821019074 PL the deadline for which expired on October 21, 2020 The subject of this audit is the fulfillment by the audited persons paragraphs 117 of the previously issued regulation dated October 21, 2019 138821019074 PL


# 641902953172
Unscheduled inspection
Start date: 2019-07-16, end date: —, duration:
Authority:
Purpose of inspection:


# 001902890410
Unscheduled inspection
Start date: 2019-07-19, end date: 2019-07-26, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the purpose of checking the implementation of paragraphs 12 of the previously issued regulation dated January 31, 2019 138820119007KP and paragraphs 121 of the previously issued regulation dated December 27, 2018 P503324224 on the elimination of identified violations of mandatory requirements due to the expiration of their execution, the purpose of this audit is to implement measures to control the supervision of the elimination of LukBelOil LLC TIN 6454044627 of identified violations of mandatory requirements reflected in the previously issued order dated January 31, 2019 138820119007KP, the deadline for which expired 290419 previously issued order dated December 27, 2018 P503324224, the deadline for which expired 27032019the subject of this audit is the fulfillment of the instructions of the state control and supervision bodies


# 001902683212
Unscheduled inspection
Start date: 2019-04-23, end date: 2019-05-27, duration:
Authority: Gosudarstvennaya inspekciya truda v Saratovskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing norms of labor law consideration of a written request from a citizen


# 001902637358
Unscheduled inspection
Start date: 2019-04-08, end date: 2019-04-19, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to control the compliance of the completed works with the mandatory requirements of the design documentation requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility based on the inspection program Case 644450917 C "Development of the Western part of the Guryanovskoye field of the Saratov region First stage" located at the address of the Russian Federation Saratov region Rivne district Tarlykovsky municipality former lands of the SEC "Tarlykovsky" the objectives of this audit are to prevent, identify and suppress violations of the legislation on urban development, including project documentation, committed by the developer, the customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, the subject of this audit is the compliance of the work and materials used in the construction of the specified capital construction facility, as well as the results of such work with the requirements of project documentation in accordance with the including the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources in accordance with the program for conducting checks on the availability of a construction permit compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 001902484028
Unscheduled inspection
Start date: 2019-01-30, end date: 2019-01-31, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is conducted in order to verify the fulfillment of paragraphs 12 of the previously issued instruction dated April 28, 2018 P15012478 on the elimination of identified violations of mandatory requirements due to the expiration of their deadlines, the task of this audit is to implement measures to control the supervision of the elimination of LLC LukBelOil TIN 6454044627 of identified violations of mandatory requirements reflected in the previously issued instruction dated April 28, 2018 P15012478 the deadline for which expired on 281018 The subject of this audit is the fulfillment of the instructions of the state control and supervision bodies


# 001902448596
Unscheduled inspection
Start date: 2019-01-24, end date: 2019-02-06, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to control the compliance of the completed works with the mandatory requirements of the design documentation requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility based on the inspection program Case 6404450917 C "Development of the Western part of the Guryanovskoye field of the Saratov region First stage" located at the address of the Russian Federation Saratov region Rivne district Tarlykovsky municipality former lands of the SEC "Tarlykovsky" the objectives of this audit are to prevent, identify and suppress violations of the legislation on urban development, including project documentation, committed by the developer, the customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, the subject of this audit is the compliance of the work and materials used in the construction of the specified capital construction facility, as well as the results of such work with the requirements of project documentation in accordance with the including the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources in accordance with the program for conducting checks on the availability of a construction permit compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 641802185575
Unscheduled inspection
Start date: 2018-11-29, end date: —, duration:
Authority: Ministerstvo stroitelstva i zhilischnokommunalnogo hozyaistva Saratovskoi oblasti
Purpose of inspection:


# 641802150071
Unscheduled inspection
Start date: 2018-11-13, end date: —, duration:
Authority: Mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Saratovskoi i Penzenskoi oblastyam
Purpose of inspection:


# 641802005481
Unscheduled inspection
Start date: 2018-10-15, end date: —, duration:
Authority:
Purpose of inspection:


# 641800494802
Unscheduled inspection
Start date: 2018-06-27, end date: 2018-07-24, duration:
Authority: Mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Saratovskoi i Penzenskoi oblastyam
Purpose of inspection: verification of the fulfillment of previously issued Orders on the elimination of violations of legislation in the field of environmental protection and violations of environmental requirements dated 23102017 3692302017 3692312017 the deadline for which expired 30052018


# 641800409565
Unscheduled inspection
Start date: 2018-05-28, end date: 2018-06-25, duration:
Authority: Mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Saratovskoi i Penzenskoi oblastyam
Purpose of inspection: The purpose of the audit is the fulfillment by LukBelOil LLC of the previously issued instruction on the elimination of violations of legislation in the field of nature management and environmental protection dated 23112017 3579155 The task of this audit is supervision in the field of waste management of production and consumption The subject of the audit is the fulfillment of the instruction on the elimination of violations of legislation in the field of nature management and environmental protection dated 23112017 3579155


# 641800189696
Unscheduled inspection
Start date: 2018-03-12, end date: 2018-03-23, duration:
Authority: Mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Saratovskoi i Penzenskoi oblastyam
Purpose of inspection: The purpose of the audit is the fulfillment by LukBelOil LLC of the previously issued instruction on the elimination of violations of legislation in the field of nature management and environmental protection dated 23112017 3679154 The task of this audit is supervision in the field of atmospheric air protection The subject of the audit is the fulfillment of the instruction on the elimination of violations of legislation in the field of nature management and environmental protection dated 23112017 36791547


# 641800073642
Unscheduled inspection
Start date: 2018-02-12, end date: 2018-02-28, duration:
Authority: Mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Saratovskoi i Penzenskoi oblastyam
Purpose of inspection: The audit is carried out in order to verify the fulfillment by LukBelOil LLC of the previously issued instruction on the elimination of violations of legislation in the field of environmental protection and violations of environmental requirements dated 23112017 367118 The objectives of this audit are to verify compliance with the requirements of the current federal legislation on geological exploration rational use and protection of subsurface resources within the framework of LukBelOil LLC's previously issued instruction on the elimination of violations legislation in the field of environmental protection and violations of environmental requirements dated 23112017 367118 The subject of this audit is the fulfillment by LukBelOil LLC of a previously issued order to eliminate violations of legislation in the field of environmental protection and violations of environmental requirements dated 23112017 367118


# 64180803058297
Unscheduled inspection
Start date: 2018-01-16, end date: —, duration:
Authority:
Purpose of inspection:


# 001800009490
Unscheduled inspection
Start date: 2018-01-19, end date: 2018-02-01, duration:
Authority: NizhneVolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this check is carried out in order to control the elimination of identified violations of the mandatory requirements specified in the Regulation dated 301/12017 476028 upon expiration of the deadline for execution, the deadline expired on 09.012018


# 64170802818927
Unscheduled inspection
Start date: 2017-11-03, end date: —, duration:
Authority:
Purpose of inspection:


# 00170802901067
Unscheduled inspection
Start date: 2017-11-22, end date: 2017-12-05, duration:
Authority: NizhneVolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: compliance with the mandatory requirements of the previously issued legal regulation 408828 on the elimination of violations during the construction of a capital construction facility dated October 20, 2017


# 00170802864779
Unscheduled inspection
Start date: 2017-11-15, end date: 2017-11-30, duration:
Authority: NizhneVolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: compliance with the mandatory rules provided for by the Urban Planning Code of the Russian Federation technical regulations and design documentation during the construction reconstruction of a capital construction facility


# 00170802673071
Unscheduled inspection
Start date: 2017-10-05, end date: 2017-10-20, duration:
Authority: NizhneVolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: compliance with the mandatory requirements provided for by the Urban Planning Code of the Russian Federation, technical regulations and design documentation for the construction of a capital construction facility


# 64170801910324
Unscheduled inspection
Start date: 2017-08-21, end date: —, duration:
Authority:
Purpose of inspection:


# 64170701817494
Unscheduled inspection
Start date: 2017-07-24, end date: —, duration:
Authority: Ministerstvo stroitelstva i zhilischnokommunalnogo hozyaistva Saratovskoi oblasti
Purpose of inspection:


# 00170701394458
Unscheduled inspection
Start date: 2017-02-16, end date: 2017-02-28, duration:
Authority: NizhneVolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the audit is carried out in order to verify the fulfillment of paragraphs 141 deadline for the elimination of violations 01022017 of the previously issued order dated 27102016 P4200 on the elimination of identified violations of mandatory requirements in connection with the expiration of their deadlines, the purpose of this audit is the implementation of measures to control the supervision of the elimination of LLC LukBelOil of identified violations of mandatory requirements reflected in the previously issued order dated 27102016 P4200, the deadline for which has expired 01022017 The objectives of this audit are to comply with the requirements of the state control and supervision bodies


# 00150600023916
Unscheduled inspection
Start date: 2015-07-09, end date: 2015-07-22, duration:
Authority: NizhneVolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the compliance of the completed works and the construction materials used, as well as the results of work performed during the construction of a particularly dangerous technically complex capital construction facility, the Prospecting and evaluation well 1 of the Zapadnoguryanovskaya Square within the Guryanovsky license area


# 00150600017759
Unscheduled inspection
Start date: 2015-07-01, end date: 2015-07-03, duration:
Authority: NizhneVolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the fulfillment of the points of violations specified in the previously issued prescription


# 00150500564695
Scheduled inspection
Start date: 2015-02-01, end date: —, duration: 20
Authority: Nizhne-Volzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Federal State supervision in the field of industrial safety


# 00150500564694
Scheduled inspection
Start date: 2015-02-01, end date: —, duration: 20
Authority: Nizhne-Volzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Federal State supervision in the field of industrial safety


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.