# 771902713208
Unscheduled inspection
Start date: 2019-05-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 771801269116
Unscheduled inspection
Start date: 2018-09-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803202480
Unscheduled inspection
Start date: 2018-08-14, end date: 2018-08-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803170962
Unscheduled inspection
Start date: 2018-07-02, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803129959
Unscheduled inspection
Start date: 2018-05-14, end date: 2018-06-01, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170803002125
Unscheduled inspection
Start date: 2017-12-19, end date: 2017-12-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802908363
Unscheduled inspection
Start date: 2017-11-27, end date: 2017-12-15, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802656760
Unscheduled inspection
Start date: 2017-10-02, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77170801921894
Unscheduled inspection
Start date: 2017-08-22, end date: 2017-09-01, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77160700083048
Unscheduled inspection
Start date: 2016-08-26, end date: 2016-08-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: Ustanovit chto nastoyaschaya proverka provoditsya s celyu ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii istecheniya sroka ispolneniya yuridicheskim licom individualnym predprinimatelem vydannogo organom gosudarstvennogo stroitelnogo nadzora predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovaniiZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 651016 ot 01072016