# 162101293146
Unscheduled inspection
Start date: 2021-10-29, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works, the construction materials used in the process of reconstruction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated October 26, 2021, case No. 12-04-2021/0098.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
The subject of this audit is: compliance with mandatory requirements and/or requirements established by municipal legal acts.
# 162004426294
Unscheduled inspection
Start date: 2020-06-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004394799
Unscheduled inspection
Start date: 2020-04-13, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161902908052
Unscheduled inspection
Start date: 2019-07-30, end date: 2019-07-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 23072019 case 121120190089the objectives of this inspection are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts. acts
# 161902841629
Unscheduled inspection
Start date: 2019-07-03, end date: 2019-07-04, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is conducted in order to determine the fact of fulfillment of the order dated 28052019 1212049901, the deadline for which expired 28062019 28052019 1212049902, the deadline for which expired 28062019 and drawing up an act based on the results of the audit. The objectives of this audit are to prevent, identify and suppress violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer performed during the construction of a capital construction facility. The purpose of this audit is to select the necessary compliance with the requirements of state control bodies, supervision bodies, and municipal control bodies.
# 161902724242
Unscheduled inspection
Start date: 2019-05-22, end date: 2019-05-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 06052019 case 121120180027the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161902427689
Unscheduled inspection
Start date: 2019-01-09, end date: 2019-01-10, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this inspection is carried out in order to determine the fact of fulfillment of the order dated 23112018 1219116801, the deadline for which expired on 24/122018 23112018 1219116802, the deadline for which expired on 24/122018 and drawing up an act based on the inspection results. The objectives of this inspection are to prevent, identify and suppress violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer performed during the construction of the facility The subject of this audit is to select the necessary compliance with the requirements of state control bodies, supervision bodies, and municipal control bodies for capital construction and work requirements of technical regulations, other regulatory legal acts, and project documentation.
# 161802332263
Unscheduled inspection
Start date: 2018-12-21, end date: 2018-12-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the reconstruction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used at the completion stage, as well as to draw up an inspection report on the completed reconstruction of the facility in accordance with the received by notification dated 13122018 9852 to the Inspection on the completion of the reconstruction of the capital construction facility, the objectives of this inspection are to prevent, identify and prevent violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. mandatory requirements and or requirements established by municipal legal acts
# 161802216572
Unscheduled inspection
Start date: 2018-12-10, end date: 2018-12-12, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules, as well as to draw up an act on the elimination of violations based on the notice received by the Inspectorate from 30112018 9318 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by the regulation from 22112018 1319048601 to 20022019 The objectives of this audit are to prevent as well as identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer. The subject of this audit is to comply with the instructions of state control bodies, supervision bodies, municipal control bodies
# 161802128114
Unscheduled inspection
Start date: 2018-11-21, end date: 2018-11-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 09042018 case 121120180027 The objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer of the work performed during the construction of the capital construction facility. The subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161802080429
Unscheduled inspection
Start date: 2018-11-13, end date: 2018-11-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: To establish that this inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules, as well as to draw up an act on the elimination of violations based on the notice received by the Inspection from 02112018 8381 02112018 8371 02112018 8389 07112018 8411 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated in the deadline set by the regulation from 21092018 1719018901 26102018 1719023901 26102018 1719023902 26102018 1719023903 to 30112018 The objectives of this audit are to prevent as well as identify and suppress violations committed by the developer customer the person carrying out reconstruction on the basis of a contract with the developer or the customer of compliance performed during the construction of the capital construction works requirements of technical regulations other regulatory legal acts and project documentation Subject of this audit is the fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 161802090537
Unscheduled inspection
Start date: 2018-11-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161801988791
Unscheduled inspection
Start date: 2018-10-22, end date: 2018-10-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: To establish that this inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation In accordance with the inspection program dated 17042018 case 171120180016, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out the reconstruction on the basis of a contract with the developer or the customer. requirements and or requirements established by municipal legal acts
# 161801342670
Unscheduled inspection
Start date: 2018-09-17, end date: 2018-09-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: To establish that this inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation In accordance with the inspection program dated 17042018 case 171120180016, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out the reconstruction on the basis of a contract with the developer or the customer. requirements and or requirements established by municipal legal acts
# 161800661372
Unscheduled inspection
Start date: 2018-08-27, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161800545535
Unscheduled inspection
Start date: 2018-07-16, end date: 2018-07-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 13042018 case 131120180018, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800503297
Unscheduled inspection
Start date: 2018-07-04, end date: 2018-07-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: To establish that this inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation In accordance with the inspection program dated 17042018 case 171120180016, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out the reconstruction on the basis of a contract with the developer or the customer. requirements and or requirements established by municipal legal acts
# 161800590352
Unscheduled inspection
Start date: 2018-07-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161800456122
Unscheduled inspection
Start date: 2018-06-18, end date: 2018-06-22, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 13042018 case 131120180018, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800410469
Unscheduled inspection
Start date: 2018-05-30, end date: 2018-06-01, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 09042018 case 121120180027, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer of the work performed during the construction of the capital construction facility. The subject of this inspection is to select the necessary compliance with mandatory requirements and or the requirements established by municipal legal acts
# 161800338972
Unscheduled inspection
Start date: 2018-05-04, end date: 2018-05-08, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 13042018 case 131120180018, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800314822
Unscheduled inspection
Start date: 2018-04-26, end date: 2018-04-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: To establish that this inspection is carried out in order to establish compliance with the requirements of Part 5 of Article 52 of the Urban Planning Code of the Russian Federation, as well as to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and design documentation, including energy efficiency requirements and the requirements for equipping capital construction facilities with metering devices for energy resources used. the construction permits comply with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation on the basis of the notice received by the Inspectorate on the start of reconstruction of the capital construction facility dated 16042018 2535 The objectives of this inspection are to prevent, identify and suppress violations of conformity committed by the developer customer the person carrying out reconstruction on the basis of a contract with the developer or the customer performed during the construction of the facility The subject of this audit is to select the necessary compliance with the mandatory requirements and or requirements established by municipal legal acts.