# 431802312310
Unscheduled inspection
Start date: 2018-12-21, end date: 2018-12-29, duration: —
Authority: Ministerstvo stroitelstva Kirovskoi oblasti
Purpose of inspection: Objectives Verification of the completed capital construction facility tasks Prevention identification and suppression of violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, Subject to compliance with mandatory requirements or requirements established by municipal legal acts
# 431802172452
Unscheduled inspection
Start date: 2018-11-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 431800067645
Unscheduled inspection
Start date: 2018-02-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 43170802837607
Unscheduled inspection
Start date: 2017-11-14, end date: —, duration: —
Authority: Ministerstvo stroitelstva Kirovskoi oblasti
Purpose of inspection:
# 43150600092862
Unscheduled inspection
Start date: 2015-08-17, end date: 2015-09-04, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kirovskoi oblasti
Purpose of inspection: comprehensive and complete consideration of citizens' complaints about violations of their rights and legitimate interests in the field of labor