# 00170701352680
Unscheduled inspection
Start date: 2017-02-14, end date: —, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 00160701158616
Unscheduled inspection
Start date: 2016-11-28, end date: —, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 772101390733
Unscheduled inspection
Start date: 2021-11-29, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772101339928
Unscheduled inspection
Start date: 2021-11-15, end date: 2021-11-26, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772101187463
Unscheduled inspection
Start date: 2021-10-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100618886
Unscheduled inspection
Start date: 2021-09-06, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100427365
Unscheduled inspection
Start date: 2021-08-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100436475
Unscheduled inspection
Start date: 2021-08-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100338774
Unscheduled inspection
Start date: 2021-07-12, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100274013
Unscheduled inspection
Start date: 2021-06-07, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100197953
Unscheduled inspection
Start date: 2021-05-11, end date: 2021-05-28, duration: 14
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772100142876
Unscheduled inspection
Start date: 2021-04-12, end date: 2021-04-30, duration: 15
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772005207080
Unscheduled inspection
Start date: 2020-11-02, end date: 2020-11-23, duration: 15
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the audit program The tasks of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development by the audited person The subject of verification is the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of project documentation identified during construction control and state construction supervision
# 772005160476
Unscheduled inspection
Start date: 2020-10-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803148246
Unscheduled inspection
Start date: 2018-05-28, end date: 2018-06-15, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803089741
Unscheduled inspection
Start date: 2018-02-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802941734
Unscheduled inspection
Start date: 2017-12-04, end date: 2017-12-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802817738
Unscheduled inspection
Start date: 2017-11-03, end date: 2017-11-08, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802714576
Unscheduled inspection
Start date: 2017-10-09, end date: 2017-10-13, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802674883
Unscheduled inspection
Start date: 2017-10-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802625960
Unscheduled inspection
Start date: 2017-09-26, end date: 2017-10-09, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701901926
Unscheduled inspection
Start date: 2017-08-14, end date: 2017-08-16, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701856589
Unscheduled inspection
Start date: 2017-08-02, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170801934565
Unscheduled inspection
Start date: 2017-08-25, end date: 2017-08-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170801930632
Unscheduled inspection
Start date: 2017-08-23, end date: 2017-09-07, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701830616
Unscheduled inspection
Start date: 2017-07-24, end date: 2017-08-04, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701828518
Unscheduled inspection
Start date: 2017-07-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701726578
Unscheduled inspection
Start date: 2017-06-19, end date: 2017-06-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701769224
Unscheduled inspection
Start date: 2017-06-30, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77170701691528
Unscheduled inspection
Start date: 2017-06-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701613006
Unscheduled inspection
Start date: 2017-05-10, end date: 2017-05-12, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701555659
Unscheduled inspection
Start date: 2017-04-19, end date: 2017-04-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701544442
Unscheduled inspection
Start date: 2017-04-17, end date: 2017-05-05, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701450130
Unscheduled inspection
Start date: 2017-03-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00170701416455
Unscheduled inspection
Start date: 2017-03-06, end date: 2017-03-14, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Ispolneniya predpisaniya ot 12122016 g 605G3327vno
# 00170701352680
Unscheduled inspection
Start date: 2017-02-14, end date: 2017-02-20, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Ispolneniya predpisaniya ot 12122016 g 605G3327vno
# 77160701234956
Unscheduled inspection
Start date: 2016-12-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160701158616
Unscheduled inspection
Start date: 2016-11-28, end date: 2016-12-12, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The list of documents required to be submitted in order to achieve the goals and objectives of the audit
# 77160701152584
Unscheduled inspection
Start date: 2016-11-22, end date: 2016-11-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77160701060607
Unscheduled inspection
Start date: 2016-10-31, end date: 2016-11-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: To establish that this audit is carried out in order to ensure that the capital construction facility meets the requirements of technical regulations and design documentation on the basis of an approved verification program, the objectives of this audit are to prevent identify and suppress violations of technical regulations and design documentation committed by the person being audited. The subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work the requirements of the technical regulations of the project documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used
# 77160700103214
Unscheduled inspection
Start date: 2016-09-01, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77160700426312
Unscheduled inspection
Start date: 2016-09-12, end date: 2016-09-16, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: cel proverki ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii postupivshego izvescheniya ot zastroischika zakazchika ili lica osuschestvlyayuschego stroitelstvo ob ustranenii narusheniiZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciipredmet proverki ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 713016 ot 08072016
# 77160700102981
Unscheduled inspection
Start date: 2016-08-29, end date: 2016-08-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: Ustanovit chto nastoyaschaya proverka provoditsya s celyu sootvetstvie obekta kapitalnogo stroitelstva trebovaniyam tehnicheskih reglamentov i proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam snaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov na osnovanii postupivshego izvescheniya ot zastroischika zakazchika ili lica osuschestvlyayuschego stroitelstvo ob okonchanii stroitelstvaZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya sootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov
# 77160601784620
Unscheduled inspection
Start date: 2016-08-11, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: